How do I track tender deadlines so I never miss one?
Keep one list of every bid you intend to work, with the closing date and time, the pre-bid meeting date, the EMD deadline and the internal date by which the document pack must be ready — and let a system, not a person, send the reminders. Corrigenda move dates, so the list has to update itself from the source.
The dates that matter on every bid
- Closing date and time — the only hard deadline. Note the time zone: GeM closes at the stated time IST.
- Pre-bid meeting — if there is one, decide attendance early.
- EMD deadline — where EMD is paid separately, its cut-off can precede the closing.
- Internal ready-by date — a day or two before closing, so an upload problem is not fatal.
- Bid validity end — when your price stops being binding.
How teams lose deadlines
- A corrigendum extended the date and the team worked to the old one, or moved on.
- The one person who knew the date was on leave.
- The documents were ready; the signatory was not.
Where iBid.Win helps
Saved filters alert you by email or Telegram when a matching bid appears; imported bids carry the latest closing date including corrigendum extensions; each bid in the workspace has assignees, stages and reminders, and the calendar shows the week's deadlines across the team.
Frequently asked
Does GeM send deadline reminders?
GeM notifies registered sellers of some events; it does not run your team's calendar. Keep your own system.
What time does a GeM bid close?
At the closing date and time stated in the bid, in Indian Standard Time.
Can a bid be submitted after the closing time?
No. The portal stops accepting submissions at the closing time.
Last checked 08 September 2026. Written from GeM's published process and this platform's own rules; the bid document and the GeM portal are the authority on any date or amount.